Tuesday 7 May 2024

Union Of India Vs Raman Iron Foundry - “It is only when a claim for damages is adjudicated upon by a civil court or an arbitrator and the breach of the contract is established and the amount of damages ascertained and decreed that a debt due and payable comes into existence; till then it is nothing more than a mere right to sue for damages . . . “

 SCI (1974.03.12) in Union Of India Vs Raman Iron Foundry [Civil Appeals Nos. 1224 & 1225 of 1973, Equivalent citations: 1974 AIR 1265, 1974 SCR (3) 556, AIR 1974] held that; 

  • “It is only when a claim for damages is adjudicated upon by a civil court or an arbitrator and the breach of the contract is established and the amount of damages ascertained and decreed that a debt due and payable comes into existence; till then it is nothing more than a mere right to sue for damages . . . “

  • "a debt is a sum of money which is now payable or will become payable in the future by reason of a present obligation"

  • "Standing alone, the word 'debt,' is as applicable to a sum of money which has been promised at a future day as to a sum now due and payable. If we wish to distinguish between the two, we say of the former that it is. a debt 'owing, and of the latter that it is debt due."

  • Therefore, no pecuniary liability arises till the Court has determined that the party complaining of the breach is entitled to damages. Therefore, when damages are assessed, it would not be true to say that what the Court is doing is ascertaining a pecuniary liability which already existed. 

  • The Court in the first place must decide that the defendant is liable and then it proceeds to assess what that liability is. But till that determination there is no liability at all upon the defendant.


Excerpts of the order;

CIVIL APPELLATE JURISDICTION: Civil Appeal No. 1330 of Appeal by special leave from the Judgment and Order dated the 22nd January, 1973 of the Delhi High Court in I. A. No. 1854 of 1972 in Suit No. 485 (A) of 1972 and Civil Appeals Nos. 1224 & 1225 of 1973.


Appeals by special leave from the Judgment and Order dated the 15th November, 1972 of the Delhi High Court in I. A. Nos. 846 and 119 of 1972 in Suit No. 158 of 1971. L. N. Sinha, Solicitor General of India Shyamala pappu & S. P. Nayar for the appellant (in all the appeals) D. G. Singhania, M. K. Garg and Shiv Khurana for respon- dent (in C. A. 1330) D. D. Sharma for respondent (in C.A.s. 1224-1225) The Judgment of the Court was delivered by BHAGWATI, J.-These appeals, raise an interesting question relating to the interpretation of cl. 18 of the General Conditions of Contract contained in the Standard Form of Contract No. D.G.S. & D. 68. That is the standard form in which contracts are entered into by the Central Purchase Organisation of the Government of India for purchase of stores from third parties described as 'contractors and the question of interpretation which arises for determination is, therefore, one of some importance, affecting as it does a large number of people who enter into such contracts with the Government of India. The facts giving rise to these appeals follow a common pattern and it would, therefore, be sufficient if we set out the facts relating to civil appeals Nos. 1221 and 1225 of 1973. They bring out clearly the point which arises for consideration in all the three appeals.


The respondent tendered for supply of certain quantity of foam compound to the appellant and its tender was accepted by the appellant by acceptance of Tender dated 16th July, 1968. The Acceptance of Tender was subject to the General Conditions of Contract contained in the Standard Form of Contract No. D.G.S. & D. 68. The only clauses of the General Conditions of Contract which are material for our purpose are cls. 18 and 24 and they read as follows:

  • "18. RECOVERY OF SUMS DUE Whenever any claim for the payment of a sum of money arises out of or under the contrat against the contractor, the purchaser shall be entitled to recover such sum by appropriating in whole or in part, the security, if any, deposited by the contractor, and for the purpose aforesaid, shall be entitled to sell and/or realise securities forming the whole or part of any such security deposit. In the event of the security being insufficient, the balance and if no security has been taken from the contractor, the entire sum recoverable shall be recovered by appropriating any sum then due or which at any time thereafter may become due to the contractor under the contract or any other contract with the purchaser or the Government or any person contracting through the Secretary, if such sum even be not sufficient to cover the full amount recoverable, the contractor shall on demand pay to the purchaser the balance remaining due.

  • "24. ARBITRATION In the event of any question, dispute,or difference arising under these conditions or any special conditions of contract, or in connection with this contract, (except as to any matters the decision of which is specialty provided for by these or the special conditions) the same shall be referred to the sole arbitration of an Officer in the Ministry of Law, appointed to be the arbitrator by the Director General of Supplies & Disposals. It will be no objection that the arbitrator is a Government Servant, that he had to deal with the matters to which the contract relates or that in the course of his duties as a Government servant he has expressed views on all or any of the matters in dispute or difference. The award of the arbitrator shall be final and binding on the parties to this contract.


Work under the contract shag, if reasonably possible, continue' during the arbitration proceedings and no payment due to or payable by the purchaser shall-be withheld on account of such proceedings.


The performance of this contract ran into difficulties and a dispute arose between the parties giving rise to claims by either party against the other. The respondent contended that the appellant had committed a breach of the contract and was, therefore, liable to pay to the respondent a sum of Rs. 2,35,800/- by way of damages. suffered by the respondent by reason of the breach of the contract. The appellant, on the other hand, said that it was the respondent who had committed the breach, of the contract and was liable to pay to the appellant by way of damages a sum of Rs. 2.28,900/- under clause 14 of the General Conditions of Contract. The Assistant Director of Supplies by his letter dated 30th March, 1971 called upon the respondent to make payment of the amount of Rs. 2,28,900/and intimated that if the respondent failed to do so on or before 30th April, 1971, the Pay and Accounts Officer, New Delhi/Madras would be authorised to recover the, same from the pending bills of the respondent in respect of other contracts. This dispute between the parties being a dispute arising out of the contract was liable to be settled by arbitration under cl. 24 of the General Conditions of Contract and the respondent, therefore, filed an application. in the Delhi High Court under s. 20 of the Indian Arbitration Act for filing the Arbitration Agreement contained in that clause. The respondent also, at the same time, made an application to the Delhi High Court for an interim injunction restraining the appellant from recovering the amount of damages claimed by it from the pending bills of the respondent. This application was, however, rejected by the Delhi High Court on the ground that it was not shown that there were any pending bills of the respondent at that time out of which the threatened recovery could be made by the appellant. The application under s. 20 of the Indian Arbitration Act was thereafter heard by the Delhi High Court and by an order dated 5th May, 1972 the Delhi High Court allowed that application and ordered the arbitration agreement contained in cl. 24 to be filed and made an order of reference to arbitration in accordance with the arbitration agreement. The claim of the respondent against the appellant for Rs. 2,35,800/- and the counter-claim of the appellant against the respondent for Rs. 2,28,900/- thus became the subject matter of reference tO arbitration. During the pendency of the arbitration some amounts became due and payable by the appellant to the respondent in respect of other contracts entered into between the parties. In view of the letter dated 30th March, 1971 the respondent apprehended that the appellant would appropriate these amounts towards recovery of the amounts of damages claimed by it even though the claim for damages was disputed by the respondent and was pending adjudication before the arbitrator. The respondent, therefore, made interim Application No. 119 of 1972 to the Delhi High Court on 17th January, 1972 under s. 41 read with the Second Schedule to the Indian Arbitration Act, 1940 praying that the status quo should be maintained and the appellant should be restrained from recovering its claim for damages from the amounts due and payable by the appellant to the respondent in respect of the pending bills. How it appears that this Interim Application No. 119 of 1972 was made in the Original Application under s. 20 of the Indian Arbitration Act, 1940 and the appellant, therefore, raised a technical objection that the Original Application under s. 20 having been disposed of, Interim Application No. 119 of 1972, as filed, could not be maintained. The respondent, in view of this technical objection raised on behalf of the appellant, filed another Interim Application No. 746 of 1972 as an independent application under s. 41 read with the Second Schedule to the Indian Arbitration Act, 1940 on 16th May, 1972 praying for the same interim relief as was claimed in the earlier Interim Application No. 119 of 1972. Both these interim applications were resisted by the appellant relying on cl. 18 of the General Conditions of Contract but Mr. Justice Avadh Bihari of the Delhi High Court, who heard these interim application, took the view that cl. 18 did not authorise the appellant to appropriate. the amounts of any pending bills of the respondent towards satisfaction of its claim for damages against the respondent, unless such claim for damages was either admitted by the respondent or adjudicated upon by arbitration or suit in civil court. The learned Judge accordingly by an order dated 15th November, 1972 allowed both the interim applications and issued an interim injunction restraining the appellant "from effecting recovery of the amounts claimed to be due from- the other pending bills" of the respondent. The appellant thereupon, with certificates obtained from the Delhi High Court, preferred Civil Appeals Nos. 1224 and 1225 of 1973 in this Court. One appeal was directed against' the impugned order in so far it related to Interim Application No. 119 of 1972 and the other in so far as it related to Interim Application No. 846 of 1972. The appellant also preferred Civil Appeal No. 1330 of 1973 against a similar order passed by the learned Judge in Interim Application No. 854 of 1972 in the other case.


There are in the main two grounds on which the learned Solicitor General, appearing on behalf of the appellant, challenged the order of Interim injunction made by Mr. Justice Avadh Bihari A.The impugned order amounted in effect and substance to an order directing the appellant to pay the amounts of the pending bills of the respondent: in respect of the other contracts and since the question of payment of the amounts of such pending bills did not form the subject matter of the reference which was pending before the arbitrator., the learned Judge had no jurisdiction under s. 41 read with the Second Schedule to make such an order and the impugned order was, therefore, outside the scope of his power and hence invalid., B.Clause 18 comes into play when there is a claim for payment of a sum of money arising out of or under the contract. It is not necessary that the sum of money must be due and payable to the purchaser. It is enough if there is a claim even for damages. Whenever, there is such claim, the purchaser is given a right under cl. 18 to recover it by appropriating "any sum then due or which at any time thereafter may become due to the contractor under the contract" or under any other contract. The appellant was, therefore, en- titled to recover the amount of its claim for damages against the respondent by appropriating the sums which subsequently became due to the respondent under other contracts, even though the claim for damages was contested by the respondent and was pending adjudication before the arbitrator. No interim injunction could be granted to prevent the exercise of such right. If interim injunction were to be granted in a case of this kind as of course merely on the ground, without anything more, that the claim for damages is pending adjudication and until it is determined in favour of the purchaser,' it should not be allowed to be recovered by the purchaser out of other sums due to the contractor, it would render cl. 18 meaningless and ineffectual and the tight to the purchaser under that clause would become illusory. of course, it would be open to the court even in such a case to grant interim injunction, if it is satisfied that the claim for damages is prima facie not well founded and the balance of convenience requires that, Pending adjudication, the purchaser should be restrained from effecting recovery of the claim for damages from out of other sums due to the contractor. But here admittedly neither of these two factors was taken into consideration by the learned Judges and the order of interim injunction made by' him cannot, therefore, be sustained. We shall proceed to examine these grounds in the order in which we have set them out.


Re: Ground A. It was common ground between the parties that the order of. interim injunction was made by the learned Judge under s. 41

(b) read with the Second Schedule to the Indian Arbitration Act, 1940. Now s. 41(b) says that the court shall have, for the purpose of and in relation to arbitration proceedings, the same , power of making orders in respect of any of the matters set out in the Second Schedule as it has for the purpose of and in relation to any proceedings before the Court and one of the matters set out in the Second Schedule is "interim injunction". The Court has, therefore, power under s.41 (b) read with the Second Schedule to issue interim injunction, but such interim injunction can only be "for the purpose of and in relation to arbitration proceedings". , The arbitration proceedings in the present case were for determination of the mutual claims of the appellant and the respondent arising out of the contract contained in the acceptance of Tender dated 16th July, 1968.


The question whether any amounts were payable by the appellant to the respondent under other contracts was not the subject matter of the arbitration proceedings. The Court obviously could not, there fore, make an interim order which, though ostensibly in form an order of interim injunction, in substance amounted to a direction to the appellant to pay the amounts due to' the respondent under other contracts. Such an interim order would clearly not be for the purpose of or in relation to the arbitration proceedings as required by s. 41 (b). But here the order of interim injunction made by the learned judge does not, expressly or by necessary implication, carry any direction to the appellant to pay the amounts due to the respondent under other contracts. It is not only in form but also in substance a negative injunction. It has no positive content. What it does is merely to injunct the appellant from recovering, suo moto, the damages claimed by it from out of other amounts due to the respondent. It does not direct that the appellant shall pay such amounts to the respondents. The appellant can still refuse to pay such amounts if it thinks it has a valid defence and if the appellant.does so, the only remedy open to the respondent would be to take measures in an appropriate forum for recovery of such amounts where it would be decided whether the appellant is liable to pay such amounts to the respondent or not. No breach of the order of interim injunction as such would be involved in non-payment of such amounts by the appellant to the respondent. The only thing which the appellant,is interdicted from doing is to make recovery of its claim for damages by appropriating such amounts in satisfaction of the claim. 'That is clearly Within the power of the Court under s. 41 (b) because the claim for damages forms the subject matter of the arbitration proceedings and the Court can always say that until such claim, is adjudicated upon, the appellant shall be restrained from recovering it by appropriating other amounts due to the respondent. The order of interim injunction made by the learned Judge cannot, therefore, be said to be outside the scope of his power under s. 41 (b) read with the Second Schedule Re: Ground B. That takes us to the second ground of challenge against the order of interim injunction. This ground of challenge is based on the proper interpretation of cl. 18. The argument of the appellant was that what is required for attracting the applicability of cl. 18 is a mere claim for payment of a sum of money arising out of or under the contract against the contractor and it is not necessary that a sum of money must be actually due and payable from the contractor to the purchaser. If the purchaser has a claim for payment of a sum of money against the contractor, he would be entitled to exercise the right given under cl. 18, even though such claim may not be for a sum due and payable but pay be for damages and it may be disputed by the contractor and may not have been adjudicated upon in a court of law or by arbitration. The purchaser can in such a case recover the amount of his claim, without resort to a court of law or arbitration, by appropriating sums due to the contractor under the same contract or under other contracts, if the claim of the purchaser is not well founded and the appropriation made by him is, therefore, unjustified, the contractor can always institute a suit or arbitration for recovering the sums due to him which have been wrongly appropriated by the purchaser and in such suit or arbitration,the court or the arbitrator, as the case may be, would examine theclaim against which appropriation has been made bypurchaser and if the claim is found to be unsustainable, set at naught the appropriation and pass a decree or award for the sums due to the contractor. But the court cannot and should not restrain the purchaserfrom exercising his right of appropriation merely because the claim against which appropriation is sought to be made by the purchaser is disputed by the contractor and is pending adjudication before a court of law or arbitrator. The court should not prevent the normal operation of cl. 18 by interfering with it, unless it appears to the court prima facie that the claim which is sought to be recovered by appropriation is not well founded and the balance of convenience lies in favour of restraining the purchaser from recovering it by appropriation. The respondent, however, disputed the validity of this construction placed on cl. 18 by the appellant and contended that though the words used in the opening part of cl. 18 are "any claim for the payment of a sum of money", which are general words of apparently wide amplitude sufficient to cover even a claim for damages arising out the contract, a proper construction of the clause read as a whole clearly suggests that these words are intended to refer only to a claim for a sum due and payable and do not take in a claim for damages which is disputed by the contractor. It is only when a claim for damages is adjudicated upon by a civil court or an arbitrator and the breach of the contract is established and the amount of damages ascertained and decreed that a debt due and payable comes into existence; till then it is nothing more than a mere right to sue for damages and it does not fall within the words of cl. 18. Moreover, cl. 18 merely provides a mode of recovery and it can have no application where a claim, even though it be for a sum due and payable, is dis- puted by the contractor and has to be established in a court of law or by arbitration: cl. 18 applies only where a claim is either admitted,or in case of dispute, substantiated by resort to the judicial process. Therefore, when the purchaser has a claim for damages which is disputed by the contractor, the purchaser is not entitled under cl. 18 to recover the amount of its claim for damages by appropriating other sums due to the contractor until the claim for damages is adjudicated upon and culminates in a decree. The appellant in the present case had consequently no right under cl. 18 to appropriate sums due to the respondent under other contracts in satisfaction of its claim for damages against the respondent, when the claim for damages was pending adjudication before the arbitrator and the learned Judge was right in restraining the appellant from doing so by issuing an interim injunction. These were broadly the contentions of the parties under this head of challenge and the question is which of these rival contentions is correct. It is true that the Words "any claim for the payment of a sum of money" occurring in the opening part of, cl. 18 are words of great amplitude, wide enough to cover even a claim for damages, but it is a well settled rule of interpretation applicable alike to instruments as to statutes that the meaning of ordinary words is to be found not. so much in strict etymological propriety of language nor even in popular use as in the subject or occasion on which they are used and the object which is intended to be attained. The context and collocation of a particular expression may show that it was not intended to be used in the sense which it ordinarily bears. Language is at best an imperfect medium of expression and a variety of meanings may often lie in a word or expression. The exact colour and shape of the meaning of any word or expression should not be ascertained by reading it in isolation, but it should be read structurally and in its context, for its meaning may vary with its contextual setting. We must, therefore, read the words 'any claim for the payment of a sum of money' occurring in the opening part of cl. 18 not in isolation but in the context of the whole clause, for the intention of the parties is to be gathered not from one part of the clause or the other but from the clause taken as a whole. It is in the light of this principle of interpretation that we must determine whether- the words 'any claim for the payment of a sum of money' refer only to a claim for a sum due and payable which is admitted or in case of disputes, established in a court of law or by arbitration or they also include a claim for damages which is disputed by the contractor.


The first thing that strikes one on looking at cl. 18 is its heading which reads: "Recovery of Sums Due". It is true that a heading cannot control the interpretation of a clause if its meaning is other- wise plain and unambiguous, but it can certainly be referred to as indicating the general drift of the clauses and affording a key to a better understanding of its meaning. The heading of cl. 18 clearly suggests that this clause is intended to deal with the subject of recovery of sum due. Now a sum would be due to the purchaser when there is an existing obligation to pay it in present. It would be profitable in, this connection to refer to the concept of a 'debt', for a sum due is the same thing as a debt due. The classical definition of 'debt' is to be found in Webb v. Stenton (1) where Lindley, L. J., said : "a debt is a sum of money which is now payable or will become payable in the future by reason of a present obligation". There must be debitum in praesenti; solvendum maybe in praesenti or in future that is immaterial. There must be an existing obligation to pay a sum, of money now or in future. The following passage from the judgment of the Supreme Court of California in People v. Arguello. (2) which, was approved by this Court in Kesoram Industries v. Commissione of Wealth Tax (3) clearly brings out the essential characteristics of a debt "Standing alone, the word 'debt,' is as applicable to a sum of money which has been promised at a future day as to a sum now due and payable. If we wish to distinguish between the two, we say of the former that it is. a debt 'owing, and of the latter that it is debt due."


This passage indicates, that when there is an obligation to pay a sum of money at a future date, it is a debt owing but when the obligation, is to pay a sum of money in praesenti, it is a debt due. A sum due would, therefore, mean a sum for which there is an existing obligation to pay in praesenti or in other words, which is presently payable.. 


Recovery-of such sums is the subject matter of cl. 18 according to the heading. That is the dominant idea running through the entire cl.18.


The language used in the body of cl. 18 also supports the view that it is with recovery of sums presently due and payable by the ,contractor to the purchaser that this clause deals. It may be noted that cl. 18 does not lay down the substantive rights and obligations of the parties under the contract. It is merely intended to provide a mode of recovery of ' a claim for payment of a sum of money arising out of or under the contract". It, therefore, postulates a claim for a sum which is due and payable, that is. presently recoverable and may be recovered by the mode therein provided. it is difficult to believe that the contracting parties could have intended that even though a sum is not due and payable by the contractor to the purchaser under the contract, the purchaser should be entitled to recover it by adopting ,the mode set out in cl.

  • 18. It is important to note that cl. 18 does not -create a lien on other sums due to the contractor or give to the purchaser a right to retain such sums until his claim against the contractor is satisfied.If merely a right of lien or retention were given to secure payment of a claim, then even if the claim were for a sum not presently due and payable, the provision perhaps would not have been so startling ,or unusual. But here the right given to the purchaser under. cl. 18 is a right to recover the amount of his claim by appropriating other sums due to the contractor and, on the, interpretation of the appellant, this can be done even if the claim is for a sum which is not due or payable in praesenti and the purchaser is otherwise not entitled to recover it. That would indeed be a highly extra-ordinary result which we would be loathe to reach in the absence of clear and compelling language. This interpretation, if accepted, would mean that as soon as a claim is made by the purchaser, it would immediately become recoverable and the purchaser would be entitled to sell off the securities of the contractor and appropriate the sale proceeds in or towards satisfaction of such claim and in case that is insufficient, recover the balance by appropriating other sums due to the contractor and if there is even then a shortfall, recover it personally from the contractor, for the last words of cl. 18 provide that "the contractor shall on demand pay to the purchaser the balance remaining due". And this consequence would ensue even if the claim is for a sum which the -contractor is under no existing obligation to pay or which is not presently payable or is disputed as regards the existence of liability or its quantum. A mere making of a claim by the purchaser would impose a liability on the contractor to pay it. That surely could -not have been the intention of the contracting parties. It would be more consonant with reason and good sense to take the view, which, as pointed out above, is plainly and indubitably supported by the language used by the contracting parties, that cl. Is does no more than merely provide an additional mode of recovery to the purchaser, and the purchaser is entitled to exercise the right conferred, under that clause only where there is a claim for a sum which is presently due and payable by the contractor. This view, indeed, becomes irresistible when we consider the last words of cl. 18, namely, "the contractor shall on demand pa to the purchaser the balance remaining due", which clearly postulate that the reference in the clause is to a sum presently due and payable by the contractor to the purchaser, so that, if any balance remains unrecovered after adopting the special mode of recovery provided in the clause, such balance must be paid by the contractor to the purchaser on demand. The appellant laid great emphasis on the use of the word 'claim' in the opening part of cl. 18 and contended that the Standard Form of Contract which was in use prior to the adoption of the present Standard Form of Contract, cl. 14, and which corresponded to the present cl. 18, opened with the words " whenever under this contract any sum of money is recoverable from and payable by the contractor", but this formula was deliberately and advisedly altered when the present Standard Form was introduced and instead, the words "whenever any claim for the payment of sum of money arises...." were substituted and this change in phraseology indicated that in order to attract the applicability of the present cl. 18 it was not necessary that there should be a sum due and payable by the contractor to the purchaser but it was enough if there was a mere claim on the part of the purchaser for payment of a sum of money by the contractor, irrespective of whether such sum of money was presently due and payable or not. This contention is, in our opinion,. wholly untenable. We do not think it is legitimate to construe cl. 18 of the contract between the parties by reference to a corresponding clause which prevailed in an earlier Standard Form of Contract. This is not a statute enacted by the Legislature where it can be said that if the Legislature has departed from the language used by it in an earlier enactment, it would be a fair presumption to make that the alteration in the language was deliberate and it was intended to convey a different meaning. It is a clause in a contract which we are construing and there, any reference to a similar or dissimilar clause in another contract would be irrelevant. The only question before us is, what does cl. 18 mean and that depends on the plain interpretation of its language in the context in which it occurs. Moreover, on a question of construction of cl. 18, mere use of the word "claim" cannot be a decisive factor. Cl. 18 has to be read as a whole, each part throwing light on the other, without any undue emphasis on one word or the other. We cannot allow our interpretation of cl. 18 to be hijacked from its true course by the use of a solitary word such as "claim", but we must arrive at the true meaning of the clause by construing it in all its parts and in its proper contextual setting. So viewed, it is clear that cl. 18 applies only where the purchaser has a claim for a sum presently due and payable by the contractor. Having discussed the proper interpretation of cl. 18, we may now turn to consider what is the real nature of the claim for recovery of which the appellant is seeking to appropriate the sums due to the respondent under other contracts: The claim is admittedly one for damages for breach of the contract between the parties. Now, it is true that the damages which are claimed are liquidated damages under cl. 14, but so far as the law in India is concerned, there is no qualitative difference in the nature of the claim whether it be for liquidated damages or for unliquidated damages. Sec. 74 of the Indian Contract Act eliminates the some-what elaborate refinements made under the English common law in distinguishing between stipulations providing for payment of liquidated damages 'and stipulations in the nature of penalty. Under the common law a genuine preestimate of damages by mutual agreement is regarded as a stipulation naming liquidated damages and binding between the parties a stipulation in a contract in terrors is a penalty and the Court refuses to enforce it, awarding to aggrieved party only reasonable compensation. The Indian Legislature has sought to cut across the web of rules and presumptions under the English common law, by enacting a uniform principle applicable to all stipulations naming amounts to be paid in case of breach, and stipulations by way of penalty, and according to this principle, even if there is a stipulation by way of liquidated damages, a party complaining of breach of contract can recover only reasonable compensation for the injury sustained by him, the stipulated amount being merely the outside limit. It, therefore makes no difference in the present case that the claim of the appellant is for liquidated damages. It stands on the same footing as a claim for unliquidated damages. Now the law is well settled that a claim for unliquidated damages does not give rise to a debt until the liability is adjudicated and damages assessed by a decree or order of a Court or other adjudicatory authority. When there is a breach of contract, the party who commits the breach does not eo instanti incur any pecuniary obligation, nor does the party complaining of the breach becomes entitled to a debt due from the other party. The only right which the party aggrieved by the breach of the contract has is the right to sue for damages. That is not in actionable claim and this position is made amply clear by the amendment in s. 6(e) of the Transfer of Property Act, which provides that a mere right to sue for damages cannot be transferred. This has always been the law in England and as far back as 1858 we, find it stated by Wightman, J., in Jones v. Thompson (1) "Exparte Charles and several other cases decide that the amount of a verdict in an action for unliquidated damages is not a debt till judgment has. been signed".. It was held in this case that a claim for damages dots not become a debt even after the jury has returned a verdict in favour of the plaintiff till the judgment is actually delivered. So also in O' Driscoll v. Manchester Insurance Committee,(2) Swinfen Eady, L. J., said in reference to cases where the claim was for unliquidated damages "in such cases there is no debt at all until the verdict of the jury is pronounced assessing the damages and judgment is given. The same view has also been taken consistently by different High Courts in India. We may mention only a few of the decisions, namely, Jabed Sheikh v. Taher Mallik,(3) S. Malkha Singh v. M/s N. K. Gopala Krishna Mudaliar(4) and Iron & Hardware (India) Co. v. Firm Shamlal & Bros.(5) 


Chagla, C. J. in the last mentioned case, stated the law in these terms:

" In my opinion it would not be true to say that a person who commits a breach of the contract incurs any pecuniary liability, nor would it be true to say that the other party to the contract who complains of the breach has any amount due to him from the other party.


As already stated, the only right which he has is the right to go to a Court of law and recover damages. Now, damages are the compensation which a Court of law gives to a party for the injury which he has sustained. But, and this is most important to note, he does not get damages or compensation by reason of any existing obligation on the part of the person who has committed the breach. He gets compensation as a result of the fiat of the Court. Therefore, no pecuniary liability arises till the Court has determined that the party complaining of the breach is entitled to damages. Therefore, when damages are assessed, it would not be true to say that what the Court is doing is ascertaining a pecuniary liability which already existed. The Court in the first place must decide that the defendant is liable and then it proceeds to assess what that liability is. But till that determination there is no liability at all upon the defendant."


This statement in our view represents the correct legal position and has our full concurrence. A claim for damages for breach of contract is, therefore, not a claim for a sum presently due and payable and the purchaser is not entitled, in exercise of the right conferred upon it under cl. 18, to recover the amount of such claim by appropriating other sums due to the contractor. On this view, it is not necessary for us to consider the other contention raised on behalf of the respondent, namely, that on a proper construction of cl. 18, the purchaser is entitled to exercise the right conferred under that clause only where the claim for payment of a sum of money is either admitted by the contractor, or in case of dispute, adjudicated upon by a court or other adjudicatory authority. We must, therefore, hold that the appellant had no right or authority under cl. 18 to appropriate the amounts of other pending bills of the respondent in or towards satisfaction of its claim for damages against the respondent and the learned Judge was justified in issuing an interim Injunction restraining the appellant from doing so.


We accordingly dismiss the appeals. The appellant in each appeal will pay the costs of the respondent all throughout, V.P.S. Appeals dismissed.


-----------------------------


FLSmidth Pvt. Ltd. Vs. Lanco Infratech Ltd. - “it is only when a claim for damages is adjudicated upon by a civil court or an arbitrator and the breach of contract is established and the amount of damages ascertained and decreed that a debt due and payable comes into existence; till then it is nothing more than mere right to sue for damages…”.

 NCLAT (2024.05.03) in FLSmidth Pvt. Ltd. Vs. Lanco Infratech Ltd. [(2024) ibclaw.in 291 NCLAT, TA (AT) No.207/2021 Company Appeal (AT) (INS) No. 1353 of 2019 ] held that; 

  • “it is only when a claim for damages is adjudicated upon by a civil court or an arbitrator and the breach of contract is established and the amount of damages ascertained and decreed that a debt due and payable comes into existence; till then it is nothing more than mere right to sue for damages…”.
  • They have rightly held that when claim and counter claims are involved Liquidator cannot decide the same and therefore the Liquidator rightly rejected the claim.


Excerpts of the order;

[Per : Jatindranath Swain, Member (Technical)]

# 1. The instant appeal has been filed under section 61 of the Insolvency and Bankruptcy Code, 2016, challenging the Impugned Order of the Adjudicating Authority / National Company Law Tribunal, Hyderabad Bench dated 15.10.2019 filed in IA No. 204/2018 and IA No. 56/2019 under section 60(5) of Insolvency and Bankruptcy Code, 2016.


Brief Facts of the case:

# 2. Pursuant to an application filed by the financial creditor under section 7 of IBC, Corporate Insolvency Resolution Process (CIRP) proceedings were initiated against the Corporate Debtor (CD), Lanco Infratech Ltd. and the same was admitted on 07.08.2017 and the Respondent herein was appointed as the Resolution Professional (RP). On an application filed by the Resolution Professional (RP), the liquidation proceedings were initiated against the said CD and the Erstwhile Respondent Mr. Savan Godiawala was appointed by the Adjudicating Authority (AA), that is, NCLT, Hyderabad.


# 3. The Appellant herein, a company incorporated under Companies Act, 1956 is an engineering company engaged in supplying complete engineering solutions and products and the associated maintenance and support services.


# 4. This being so, the Corporate Debtor (CD) issued a purchase order on the Appellant for supply of certain systems including pipe conveyor system, firefighting system, and associated spares and accessories inclusive of design, engineering, manufacturing, testing, packing and forwarding, delivery and commissioning spares as applicable for external coal handling plant as per the technical specification of the CD and also awarded a work order for erection, supervision, commissioning and conducting of performance guarantee test of the said systems for a total value of Rs. 95.17 crore.


# 5. While the Appellant was engaged in executing the contract the CD did not open an irrevocable letter of credit equivalent to Rs. 73.602 crores, did not take delivery of supplies made ready and did not issue clearance for material dispatch of the manufactured items under various pretexts.


# 6. Meanwhile the CD was put under CIRP and the Appellant filed a claim before the Insolvency Resolution Professional (IRP) for a sum of Rs. 71.09 crore by filing Form-B on 21.08.2017. The same was examined by the IRP and he confirmed that a sum of Rs.13.47 crore is payable and asked the Appellant to clarify the difference of Rs. 57.65 crore with sufficient supporting documents to corroborate the same. This being so, the claim was later rejected by RP which was challenged by the Appellant before AA / NCLT, Hyderabad in I.A. No.204/2018. While the said IA was pending, the CD went into liquidation as per orders of AA and the RP was appointed as the liquidator. Pursuant to the public announcement made by the Respondent as the Liquidator, the Appellant herein submitted a claim for sum of Rs. 31.71 crores in Form-C on 26.09.2018. The said claim was rejected by the Respondent vide his email dated 12.12.2018. Challenging the rejection, the Appellant filed an appeal under section 42 of IBC and the same was numbered as I.A. No.56/2019.


# 7. Both the IAs were heard by AA/ NCLT, Hyderabad and a common order was passed on 15.10.2019 dismissing both the applications.


Submissions by the Appellant

# 8. The Appellant states that the Respondent / CD, did not perform its part of the contract from its inception and did not establish the letters of credit as contemplated; further the CD did not take delivery of the materials made ready for dispatch at the Appellant’s vendors’ facilities and did not issue Material Dispatch Clearance Certificate to the Appellant for making dispatches under the purchase order even though the Appellant did not commit any breach of contract. Ultimately because of non-performance of CD, the end user TANGEDCO cancelled the contract. However, because of the contractual obligations and because of the works done pursuant to the work order given by CD for which payments became due from the CD, the Appellant became an Operational Creditor (OC) to CD.


# 9. When the CD was moved into CIRP, the Appellant preferred a claim of Rs. 71.09 crore to RP. The RP replied to him admitting dues of Rs.13.47 crore as per the ‘Books of records of CD’ and asking him to justify the balance claim of Rs.57.65 crore with sufficient supporting documents to corroborate the same. Thus, this is a categorical admission on part of the Respondent that CD owes at least Rs. 13.47 crore to the Appellant. But this was later repudiated by the Respondent in the role of RP and later in the role of liquidator and instead, the Respondent / Liquidator issued a reply stating that a sum of Rs.1.51 crore was due and payable by the Appellant to the CD. It is the contention of the Appellant that after having accepted the claim in part, it is not open to the Respondent to reject the claim later and that he has failed in his duty as liquidator.


# 10. The Appellant further contends that the AA has erred by;

  • a. overlooking the initial acknowledgement of the RP of the dues to the tune of Rs.13.47 crore, payable to the Appellant and by merely accepting the statement of the Respondent / Liquidator that the dues are disputed and there are claims and counter claims and, on that basis rejecting the application of the Appellant,

  • b. not considering the fact that the Appellant had performed its obligations under the Contract and the CD cannot walk away from its obligations of payment for the work done,

  • c. coming to a conclusion of rejection of application made by the Appellant by observing that the Liquidator cannot decide on the dues to the Appellant / OC when claims and counter claims are involved and that dispute if any between the CD and the OC has to be settled by the competent Civil Court without assigning any reason, even though power has been conferred on the AA under section 42 of IBC to adjudicate on the same.


# 11. On the above grounds the Appellant prays the Tribunal to set aside the orders of AA / NCLT, Hyderabad and to order fresh assessment of the claim of the Appellant.


# Submissions by the Respondent:

# 12. The Respondent states that the Appellant first filed a claim of Rs. 71.09 crores before RP. The RP verified the claim and determined that in fact an amount of Rs.1.51 crore, is payable by the Appellant and therefore rejected the claim against which, the Appellant has filed IA No. 204/2018. The Respondent states, that there is no contradiction between earlier letter sent acknowledging a due of Rs.13.47 crore and this rejection because the former was based on available materials and the latter was based on verification of all records of CD.


# 13. The Respondent has stated that the Liquidator has acted in accordance with the Code and IBC (Liquidation process) Regulations, 2016, in form of consolidation of claims, verification of claims and admission / rejection of claims without any lapse. In view of the provisions of the said Regulations, Liquidator is required to only verify the claims based on the information available and does not sit in adjudication of the disputes which may be pending between the CD and the OC and that adjudication of a dispute is not within the scope and ambit of the powers of the Liquidator. Accordingly, the new Liquidator would only be able to admit such claims as are borne out by the terms of contract entered into between the CD and the OC, or based on a statutory obligation or as reflected in a decree of a Court or Tribunal. In this case the claim of the Appellant is based on non-performance of its part by the CD and therefore the claim for damages would first need to be adjudicated upon by a Civil Court or Arbitrator for the ‘Debt’ to even come into existence. The new Liquidator has cited the decision of Hon’ble Supreme Court in the case of Union of India v Raman Iron Foundry AIR 1974 SC 1265, wherein, it has been held that “it is only when a claim for damages is adjudicated upon by a civil court or an arbitrator and the breach of contract is established and the amount of damages ascertained and decreed that a debt due and payable comes into existence; till then it is nothing more than mere right to sue for damages…”. The Respondent contends that she has been guided by this principle and duly conducted the process of consolidation, verification and admission / rejection of claims.


# 14. The new Liquidator has further stated, that she has not allowed the claims made against the items ‘goods ready for dispatch but not actually delivered’, ‘claim against work in progress’, claim against goods under manufacturing’, ‘GST when no tax invoice issued’ and ‘interest’, as there is no invoice or any other document to establish liability on part of CD as on 27.08.2018. She has stated that in the absence of invoices / dispatch documents existing in the records of CD, the claims of Appellant could not be substantiated. Moreover, strictly as per the terms and conditions of the Purchase Order, no amount was found to be payable by the Respondent. She has further stated that the email informing the Appellant that an amount of Rs.13.47 crore was showing as due to the Appellant does in no manner communicate the determination made by the RP on the claim submitted by the Appellant as the job of RP is not to simply rely on the books of the CD to determine the claims and that, had that been the case the entire exercise of submission and subsequent verification of claims would not be required at all.


# 15. In her further submissions she has stated that the Corporate Debtor (CD) has been sold as a Going Concern in auction on as is where is basis in form of an Acquisition Plan and the Plan has been approved by AA in its order dated 26.09.2022 in IA561/2022 of CP(IB)No.111/7/HDB/20217. Accordingly, the Board of CD has been reconstituted and she as Liquidator has no powers to entertain any claim received at this point of time. Hence the present appeal is a futile exercise with the aim to set off the receivables against the payables and that is why the appellant has not made the Acquirer, a necessary party.


# 16. Finally, the Respondent cites the order passed by Hon’ble Supreme Court in the matter of Arun Kumar Jagatramka Vs. Jindal Steel and Power Ltd. & Anr., in Civil Appeal No. 9664 of 2019 and states that the doctrine of ‘clean slate’ is applicable to this case, also.


Analysis & Findings

# 17. It is the Appellant’s case that the CD having awarded the purchase order and the work order failed to honor its obligations and therefore, the Appellant could not get the expenditure incurred by it on these accounts to the tune of Rs.31.71 crore from the CD and therefore, it should be considered a debt due to be repaid by the CD and that the RP having admitted an amount of Rs.13.47 crore, payable by CD, to the Appellant, later changed his position to Rs.1.51 crore, as receivable from the Appellant to CD in contravention of the provisions of Insolvency and Bankruptcy Code, 2016 and the Liquidation Regulations. It is also the grievance of the Appellant that the Liquidator did not adjudicate the claims contrary to the provisions contained in sections 38,39 & 40 of Insolvency and Bankruptcy Code, 2016.


# 18. The Respondent / Liquidator fairly addresses these points by stating that the items of claim not admitted by her as ‘due payable’ are those for which no documents such as invoice / dispatch documents were available in the records of CD and which were not also provided by the Appellant. She has also fairly answered the point by stating that the disallowed claims could be due to non-performance of CD which will require adjudication by a competent Civil Court / Arbitrator, before they can be translated into ‘Dues’ within the framework of IBC and has cited the relevant law in form of a decision by the Hon’ble Apex Court to support her assertion. It is also seen that the Respondent / Liquidator has given sufficient reasons for disallowing the claim of the Appellant in her letter to the Appellant.


# 19. It is also seen that the AA / NCLT, Hyderabad have dealt on these issues in detail and given succinct reasons as to why they have accepted the submission and reasoning of the Liquidator as to why she has rejected the claim of the Appellant. They have rightly held that when claim and counter claims are involved Liquidator cannot decide the same and therefore the Liquidator rightly rejected the claim.


# 20. In view of the above, it is concluded by this ‘Tribunal’, that the instant Appeal in TA (AT) No. 207/2021 (CA (AT) (INS) No.1353/2019) is devoid of merits and deserves to be dismissed and is accordingly dismissed with liberty given to the Appellant to pursue his remedies in appropriate forums. No costs.

-----------------------------